Dear Experts,
We are facing a strange issue with work items (asynchronous task). We use
this for PR release.
In recent times, it is been observed that user is executing the workitem &
approving the PR through ME29N. The PR actually moves to next approval level
& a new instance of workflow is created as it should be but the workitem
remains in user's inbox & the workflow will be pending in inbox. When I
checked the workflow log the work item status is shown as "In Process".
As a workaround, using workflow administrative tools I can complete the
workitem & complete the workflow without any impact.
I could not understand why workitems are hanging even when user is executing
it & going back from ME29 screen after saving the PR. This is happening with
no. of users & also not always.
I have checked the dumps also & there are none at the given execution time
as per workflow log. Can it be a issue with terminating events? We have not
activated the event log in Production system & thus cannot track the events.
Any inputs will be highly appreciated.
--
Regards,
Shaurya Jain
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://mailman.mit.edu/pipermail/sap-wug/attachments/20110428/4c962953/attachment.htm
More information about the SAP-WUG
mailing list