Dynamic Parallel Processing with Modeled Deadline Monitoring
Florin Wach
florin.wach at gmx.net
Tue Jan 12 01:38:07 EST 2010
Hi Paul,
I'd say that you need to wrap around a Workflow Pattern that holds the single ECN Decision step and the deadline monitoring.
The "Set-to-obsolete" process control seems to gather all existing workitems that sit on that node and sets them to obsolete. That won't happen when you use distinctive pattern childs.
Best wishes,
Florin
-------- Original-Nachricht --------
> Datum: Mon, 11 Jan 2010 21:57:05 -0500
> Von: "Paul Borriello" <pborriello at yahoo.com>
> An: sap-wug at mit.edu
> Betreff: Dynamic Parallel Processing with Modeled Deadline Monitoring
> Hi All:
>
> I have a requirement to perform an ECN Decision Step, with Dynamic
> Parallel
> processing, for 4 approvers, including Modeled Deadline Monitoring. The
> Dynamic Parallel Processing works fine. My issue is with the Modeled
> Deadline Monitoring. When the deadline hits, I set the Approval Workitem
> to
> Obsolete via Process Control. For one of the Approvers, it sends out the
> Deadline Email and then ends the WF for all of the Approval Workitems,
> even
> if they are not in Deadline. If I do not set the Workitem to Obsolete,
> the
> Deadline Approval Workitem will not loop back to the Approver Inbox until
> the other three Approval Processes have completed.
>
> When I remove the Dynamic Parallel processing the Deadline Monitoring
> process works fine.
>
> Any thoughts or ideas on how to remedy this situation?
>
> Thanks in advance for you responses.
>
> Regards,
> Paul
>
> Paul Borriello
> PAB Consulting, LLC
> 973-635-3412-office
>
>
More information about the SAP-WUG
mailing list