All,
 
I have a workflow with 2 simpels tasks, the first is a dialog step. I
test the workflow and go to my inbox in the CRM webclient and I see task
1. When I execute this task, the status of the workitem in the backend
CRM system is directly set to completed, so the workflow continues to
step 2. But I want it to continue to step 2 after I ended step 1 (like a
'normal' workflow would).
 
I saw some customizing for "Taskspecific navigation" where I can mark a
checkbox for "Application handling" which handles the completion/status.
But now there are 2 problems:
1. the method in my task is not executed but a different task (I've read
that this is additional customizing but this is complex).
2. in case I have checked the Application handling chekbox, the task
will not complete anymore.
 
How can I accomplish that my workflow tasks works the same way in the
Webclient as in the GUI?
 
Kind regards,
Robert
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://mailman.mit.edu/pipermail/sap-wug/attachments/20090918/203df1e4/attachment.htm


More information about the SAP-WUG mailing list