Tom,

 

There are multiple ways to handle this.  One simple way is to choose the
deadline tab of your choice, do not model the deadline and you will see
a 'Recipient of message when latest end missed'.  You can put a rule in
here to find the 2nd level or use an expression if the approval agents
are captured already.

 

In this case you are correct that once one selects, the workitem is
removed from the other's work list.

 

Regards,

Thomas Maue

________________________________

From: sap-wug-bounces at mit.edu [mailto:sap-wug-bounces at mit.edu] On Behalf
Of Simon, Tom
Sent: Tuesday, November 04, 2008 7:39 AM
To: sap-wug at mit.edu
Subject: Re: Deadline Monitoring Scenario

 

Shai,

        Thank you for the help with the determining the next level agent
for a deadline monitoring scenario.  I created a rule as you suggested ,
using a "z" version of function module SWX_GET_MANAGER.  I modifed the
source code to repeat getting the immediate superior, first for the
initiator, then for the initators superior.

This rule  works in obtaining the next level manager. 

 I have another question on the deadline scenario.  The requirements are
that the 2nd level approver receives the approval task if the 1st level
approver does not complete the workitem.  Is it possible to send the
same workitem to this 2nd level approver when the deadline has passed
or do I have to execute a new approver step using the same task senario
that was used for the 1st level approver.  The reason I am asking is
that if I there is a way to send the same workitem to the second level
approver after the deadline has passed I assume that when either
approver selects the workitem it should be removed from the other
approvers worklist.  Otherwise,  I am creating a new workitem for the
second approver and must decide to obsolete the original workitem in the
1st approvers worklist.  If I didn't obsolete the original workitem it
appears to me that I would then have two different workitems out there
waiting to be completed by two different agents?  What do you think? 

 Tom 

       




-----------------------------------------
This transmission is intended only for use by the intended
recipient(s). If you are not an intended recipient you should not
read, disclose, copy, circulate or in any other way use the
information contained in this transmission. The information
contained in this transmission may be confidential and/or
privileged. If you have received this transmission in error, please
notify the sender immediately and delete this transmission
including any attachments.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://mailman.mit.edu/pipermail/sap-wug/attachments/20081104/c32de814/attachment.htm


More information about the SAP-WUG mailing list