Material Reservation Workflow (IKhan)
Shai Eyal
shai.eyal at yahoo.com
Sun Jul 1 13:51:49 EDT 2007
IKhan,
The are few alternative to approach this process. First take into account that there's no standard event RESERVATION.CREATED - you have to build you own.
What I've done several time to simplify the issue:
Reservation created -> WF triggered.
Approver markes for deletion the items he wishes to reject or change quantities.
Reservation creator is notified by email.
Warehouse staff has workitem for goods issue with reference to reservation in MIGO.
Such means that if that there's no remaining - goods issue is for the whole approved reservation.
If the requestor wishes he can create another reservation.
BTW, you can automate the deletion indicator marking in case the approver reject to whole reservation.
Hopes that's help.
Regards,
Shai Eyal
SAP Logistics senior consultant
SAP Workflow specialist
----- Original Message ----
From: "sap-wug-request at mit.edu" <sap-wug-request at mit.edu>
To: sap-wug at mit.edu
Sent: Sunday, 1 July, 2007 7:10:26 PM
Subject: SAP-WUG Digest, Vol 32, Issue 1
Send SAP-WUG mailing list submissions to
sap-wug at mit.edu
To subscribe or unsubscribe via the World Wide Web, visit
http://mailman.mit.edu/mailman/listinfo/sap-wug
or, via email, send a message with subject or body 'help' to
sap-wug-request at mit.edu
You can reach the person managing the list at
sap-wug-owner at mit.edu
When replying, please edit your Subject line so it is more specific
than "Re: Contents of SAP-WUG digest..."
Today's Topics:
1. Material Reservation Workflow (IKhan)
----------------------------------------------------------------------
Message: 1
Date: Sun, 1 Jul 2007 15:39:43 +0300
From: IKhan <ikhansap at gmail.com>
Subject: Material Reservation Workflow
To: "SAP Workflow Users' Group" <SAP-WUG at mit.edu>
Message-ID:
<fff808000707010539g7258d090w925d65c118be0610 at mail.gmail.com>
Content-Type: text/plain; charset="iso-8859-1"
The scenario is when ever a Reservation is created (MB21) the goods movement
should be blocked and should be sent for approval.
The approver on executing the work item will be taken to MB22 transaction
where he have to select the items for which goods movement is allowed
(enable a check box) which means those items are approved.
The problem is say if there are 5 line items in the reservation and if the
approver approves only 3 then he can approve the remaining after two days or
one week or he will approve only 3 items remaining he is not interested in
approving .
How to control this in workflow how come we will know that the approver is
interested in only 2 times and remaining is rejected or the approver will
approve the items later..
Any Clue??
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://mailman.mit.edu/pipermail/sap-wug/attachments/20070701/3b7a362f/attachment-0001.htm
------------------------------
_______________________________________________
SAP-WUG mailing list
SAP-WUG at mit.edu
http://mailman.mit.edu/mailman/listinfo/sap-wug
End of SAP-WUG Digest, Vol 32, Issue 1
**************************************
___________________________________________________________
Yahoo! Mail is the world's favourite email. Don't settle for less, sign up for
your free account today http://uk.rd.yahoo.com/evt=44106/*http://uk.docs.yahoo.com/mail/winter07.html
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://mailman.mit.edu/pipermail/sap-wug/attachments/20070701/38f35ed5/attachment.htm
More information about the SAP-WUG
mailing list