Hi Gregory,
I've a feeling I'm asking the obvious, but can you not make the update
step a background task?
Cheers
Mike
Gregory Utley wrote:
> All,
>
>
>
> A question to all: We are soon implementing the SAP Portal. For the
> most part, we’ve had no problems with workflow applications in the
> portal environment, and the consolidation of agent approval
> notifications in the UWL is an improvement over using system dependent
> SBWP inboxes.
>
>
>
> The one major downside for workflow in the portal (specifically the UWL)
> is the loss of “synchronous dialog chain” processing (OSS Notes 794439
> and 487649). The standard SAP travel expense workflow depends upon a
> two-step approval process (approve, then update the employee master) via
> workflow. With the loss of synchronous dialog processing, the “update”
> step goes into READY status in the UWL instead of just executing
> automatically as it did before. The bottom line: the approver must
> approve twice.
>
>
>
> I wrote a program that will run periodically in background to identify
> these READY update tasks and trigger them. This solves the problem (the
> approver only approves once), but it’s not an optimum solution since it
> leaves the update task in the approver’s UWL inbox until the background
> program runs.
>
>
>
> If anyone else has run into this problem and solved it in a more
> efficient way, I’d love to hear from you.
>
>
>
> **Greg Utley**
>
> **C****i****TR****!****X Systems, Inc.**
>
> **SAP Development Team**
>
>
>
>
>
>
> ------------------------------------------------------------------------
>