Workitem requested start

Michael Pokraka workflow at quirky.me.uk
Tue May 20 09:14:44 EDT 2003


So... jsut set it to 8 minutes!
On a more serious note, your deadline granularity is determined by the scheduling of the monitor job SWWDHEX. If it runs ad hoc - i.e. when a deadline is due, then you'd be as accurate as your SAP scheduler can be - i.e. you may have a few seconds delay, or perhaps more f no bg processes are available.
If it's scheduled periodically - e.g. every 5 minutes, then you can only be accurate to witin 5 minutes. If you have too many deadlines (as this type of sceanrio might suggest), then the first option becomes unfeasible as you may end up scheduling too many jobs - which may result in the minutes' delay you see - and you should rather go with periodic scheduling anyway.
 
HTH
Cheers
Mike
 
 
On Tue, May 20, 2003 at 09:02:15AM -0400, Balasubramaniam, Swaminathan wrote:
> All,
> I have a step that has a requested start of nine minutes after the Work item
> is created. However, the actual start is always 10 minutes. When I look in
> the log, it says requested start is 9 minutes after the work item creation
> time but the actual start is 10 minutes after the creation time. Is 10
> minutes the minimum delay I can have or am I doing anything wrong. I am on a
> 46B system.
>
>
> Thanks
> Swami
 