Another way is via SE37, SWW_WI_STATUS_CHANGE_NEW. Execute it and fill
in the WI ID, change status to ERROR. (Or you can write a little ABAP to
do this).
Than you can restart using SWI2_DIAG.
 
Can you see a trend.... we've all been there :-)
 
Cheers
Mike
 
On Wed, Mar 19, 2003 at 10:40:51AM -0600, Richard Marut wrote:
> Shane,
>
> You may be able to restart the work item by displaying the task and
> going to the technical work item display, setting it to change and
> selecting 'replace' from the work item menu. I've done this with work
> items that were hanging which displayed 'executed automatically' but
> remained in the users inbox.
>
> Richard...
>
>
> -----Original Message-----
>> From: SAP Workflow [mailto:Owner-SAP-WUG at MITVMA.MIT.EDU] On Behalf Of
> Van der Burg, Jeroen JA SITI-ITPSEE
> Sent: Wednesday, March 19, 2003 9:31 AM
> To: SAP-WUG at MITVMA.MIT.EDU
> Subject: Re: Deadline - waiting tasks
>
> Hi Shane,
>
> 1. Deactivation of the deadline monitoring job can happen when it
> collides with a particular other job. There is a note for this which
> prevents it from happening. Implement this ASAP.
>
> 2. We had to restart the stopped workflows (everything that was waiting
> for a deadline to be reached at the time) manually. Not much fun.
>
>
> Regards,
>
>
> Jeroen
>
> -----Original Message-----
>> From: Shane Burns [mailto:Shane.Burns at boimail.com]
> Sent: 19 March 2003 16:07
> To: SAP-WUG at MITVMA.MIT.EDU
> Subject: Deadline - waiting tasks
>
>
> Hiya,
>
> I have a problem with deadlines on my Annual Leave with HTML workflow,
> usually I would search the archives for a solution before annoying
> anyone
> but the site seems to be down.
>
> The Annual Leave with HTML (WS20000081) calls another workflow to lock
> an
> employee record - Find employee and lock (WS1200003).
> The standard task within this workflow Lock Employee (TS20000150) has a
> requested start deadline set up of one minute.
>
> Before this deadline is reached it is in a process of waiting, however
> my
> problem is that somehow on the 6th of March the scheduled job for
> deadline
> monitoring was turned off, I only reactivated it on the 14th of March.
>
> But this has resulted in a large number of the above tasks stuck in a
> waiting process, is there any way I can execute them so they will
> complete,
> I thought turning the scheduled job back on would have completed them
> but
> it has not.
> I will be looking into why the job was stopped and making sure it
> doesn't
> happen again, but I am lost with the "waiting tasks"
> Any ideas????
>
> Thanks,
>
> Shane Burns
> Bank of Ireland, Fastnet Project
> 1-3 Westmoreland Street, Dublin 2
>
>
>
>
> ********************************************************************
> This email and any files transmitted with it are confidential and
> intended solely for the use of the individual or entity to whom they
> are addressed. If you have received this email in error please
> notify us immediately at MailMonitor at isismail.ie and delete this E-mail
> from your system. Thank you.
> It is possible for data transmitted by email to be deliberately or
> accidentally corrupted or intercepted. For this reason, where the
> communication is by email, the Bank of Ireland Group does not accept
> any responsibility for any breach of confidence which may arise
> through the use of this medium.
> This footnote also confirms that this email message has been swept
>  for the presence of known computer viruses.
> ********************************************************************
 


More information about the SAP-WUG mailing list