'Complete' status for Synchronous method
Swami Bala
swam_in at hotmail.com
Fri Feb 14 12:28:25 EST 2003
Sorry I didnot mention this before. We donot want to have this option
checked since it is one more screen for the Managers and Directors !!!.
I need to look at some other option of doing exactly the same logic but
without 'Confirm end of Processing'.
Thanks for your suggestions
Swami Bala
>Swami,
>Maybe what you need is the "Confirm End of Processing" to be checked. This
>will allow the user to execute the work item which will change status to
>executed but will not change to completed until they select the complete
>option. This does allow the work item to be executed several times though.
>Rgs,
>Susie
>
> -----Original Message-----
>From: Swami Bala [mailto:swam_in at hotmail.com]
>Sent: Friday, February 14, 2003 10:54 AM
>To: SAP-WUG at MITVMA.MIT.EDU
>Subject: 'Complete' status for Synchronous method
>
>Hello All,
>
>I am confused at the 'Complete' status of the workItem when it is a
>synchronous method. I have a task with sync. method and this seems to work
>fine if the application is saved. But when the user just clicks the back
>arrow button without saving it, the work item goes into 'Complete' status
>and dissapears from Inbox. I donot want a asynch.method since i am passing
>parameters from the method back to wflow. How does defining a terminating
>event in synch. method works ?
>Thanks
>
>Swami Bala
>
>
>
>
>_________________________________________________________________
>MSN 8 with e-mail virus protection service: 2 months FREE*
>http://join.msn.com/?page=features/virus
_________________________________________________________________
MSN 8 helps eliminate e-mail viruses. Get 2 months FREE*.
http://join.msn.com/?page=features/virus
More information about the SAP-WUG
mailing list