Business Object FIPP

Nat 4 Govender ngovender4 at toyota.co.za
Mon Oct 14 08:20:19 EDT 2002


Hi All,
 
 
Problem we are faced with :
 
1.    User created a parked document.
2.    User changes a parked document, via transaction FBV2.
3.    User does not save the document but does a "Document Check" and
"Document Complete" no new workflow starts but the document is updated with
the change.
4.    When the users change document and saves it.  The old workflow is
terminated and a new one starts where the user
      has to perform a "Document Check and a "Document Complete".
5.    On doing the "Document Check" and "Document Complete" a new release
strategy.
 
 
Does anyone knows how we can also start a new workflow if the user decides
to use option 3
.
 
There is an event in Business Object "FIPP"  called "COMPLETION".
Is this event generated by performing a "Document Complete" within a
finance transaction?
 
 
 
(Embedded image moved to file: pic27644.jpg)
 