Event linkage activated but workflow doesn't start
Aydin, Kemal (Kemal)** CTR **
aydink at lucent.com
Tue May 14 14:22:11 EDT 2002
Francine,
This might be happenning due to a missing CTS on the production environment. Did you verify if all the CTSes related with the Workflow Environment have been imported to the production system.
A tip to find Workflow CTSes:
* Goto table E071K ( in SE16 ) and display all entries with the OBJNAME = 'SWETYPECOU' . ( SWETYPECOU is the table that stores : Type Linkage Events - Receiver ).
* Execute this in both TST and Production environments, the differences in the CTS numbers ( field TRKORR ) might be the cause of this problem.
Regards,
Kemal Aydin
> -----Original Message-----
>> From: Brooks, Fran [SMTP:fbrooks at fujigreenwood.com]
> Sent: Tuesday, May 14, 2002 2:08 PM
> To: SAP-WUG at MITVMA.MIT.EDU
> Subject: Event linkage activated but workflow doesn't start
>
> Hi all,
>
> I am new to workflow and new to the list server. I am currently in a 31H
> environment. I am having problems getting my workflow to start. In my
> production environment in SWE2, I see my object (Z_BUS2032),
> event(EDI_CREATED) and receiver type (WF99900017). When I simulate the
> event(Z_BUS2032.EDI_CREATED) using SWU0, the system indicates that
> WF99900017 is a "task which do use this event". When I perform the same
> action in my development and test environment, the systems indicated that
> WF99900017 is a "Potential task to be started - Successfully started". I
> thought that because the event linkage table is set I shouldn't be having
> any problems. Any ideas as to where I have gone wrong?
>
> All suggestions are welcomed and appreciated.
>
> Francine Brooks
> SAP Programmer Analyst
> Fuji Photo Film, Inc.
> SBP (Strategic Business Processes)
> 864-942-5459