I could be wrong here, but as far as I know workitem texts are handled =
as
pretty much the rest of the workflow definition: A runtime version will =
be
created when the workflow is started to ensure integrity of the =
workflow
instance. The workitem text with replaced variables will be stored when
created and not changed for the lifetime of the workflow instance.
 
Hth,
Stephan
 
-----Urspr=FCngliche Nachricht-----
Von: Alon Raskin [mailto:araskin at 3i-consulting.com]
Gesendet: Mittwoch, 3. Juli 2002 23:01
An: SAP-WUG at MITVMA.MIT.EDU
Betreff: Re: Deadline Monitoring - Replace step information
 
 
I could be way out here but I though that If you changed the text of =
the
task (I hope you didn't create a new task) and transported it, when it
arrives in the users inbox it will display the updated text. I haven't =
read
this anywhere but I am pretty sure that I remember seeing this. I guess =
the
only thing to do is to go into your QA environment and test this.
 
If I am wrong then I guess you could write some sort of program that =
reads
all the current items and kicks off a new workflow for each one.
 
Regards,
 
Alon Raskin
3i Consulting Group
e: araskin at 3i-consulting.com
w: http://www.3i-consulting.com
 
 
-----Original Message-----
From: SAP Workflow [mailto:Owner-SAP-WUG at MITVMA.MIT.EDU]On Behalf Of =
Snyder,
Brian
Sent: Tuesday, July 02, 2002 6:36 PM
To: SAP-WUG at MITVMA.MIT.EDU
Subject: Deadline Monitoring - Replace step information
 
Hi, we are working with release 4.6C.
 
I have a WF that sends an email to employees at a certain date in time.
This is controlled by a email step with deadline monitoring activated.
There was a problem with the email text that was originally created and =
this
has been fixed now.  BUT the current work items that are waiting with =
their
deadline monitoring still contain the old email message.  How do I =
replace
the email text with the new text on these work items.  Can I recreate =
these
work items somehow without restarting the WF?  Also, this may have =
affected
many emails tasks(1000+).
 
Any help would be appreciated,
 
Brian Snyder
Business Information Systems
WaferTech
TEL: 360-817-3141
bsnyder at wafertech.com
 