Workflow Job SWWDHEX

David Weston weston at clockwork.ca
Tue Apr 9 20:24:58 EDT 2002


Maybe check you have enough batch work processes ? If they say its waiting
then all the background processes maybe used.
 
Just a thought
 
Dave
 
----- Original Message -----
From: "Smith, Cassaundra" <Cassaundra.Smith at anheuser-busch.com>
To: <SAP-WUG at MITVMA.MIT.EDU>
Sent: Tuesday, April 09, 2002 2:52 PM
Subject: Workflow Job SWWDHEX
 
 
> Workflowers,
>
> We are on SAP 4.6c.  This job, SWWDHEX, is setup via the workflow
configuration
> to monitor deadlines on workitems.  Our BASIS team is claiming that when
this
> job runs it goes into a SLEEP/WAIT status which they say is a NO NO in
> production.  We are currently having this problem in our test system.  One
of
> our workflow developers is testing a workflow whereas one of the task
would,
> normally in the AB1 environment, wait 24 hours before forcing the workitem
> status into a  'Ready' status. But because of testing, we don't want to
wait 24
> hours, so we set the job to run every 6 minutes.   My understanding is
that
> while a workitem is waiting for its deadline to be reached, the workitem
itself
> is in a 'Wait' status in the SWWWIDH table.  Could this workitem status
possibly
> be the same status that our BASIS folks are seeing in the job log.  Can
anyone
> spread any light on this.  Has anyone experienced this problem before.
>
> Thanks,
>
> Casey
>
>
>
 


More information about the SAP-WUG mailing list