"Item not covered by a release strategy"

Sheth, Neeraja Neeraja.Sheth at fnc.fujitsu.com
Thu Jul 12 17:08:15 EDT 2001


Do let me know how you resolve this - it is intriguing.
 
You must have looked, but I have to ask - has anyone played with the validity end date of your classification?
 
 
Regards
 
Neeraja
 
 
> -----Original Message-----
>> From: Sherman S. Wright [SMTP:swright at lsil.com]
> Sent: Thursday, July 12, 2001 12:45 PM
> To:   SAP-WUG at MITVMA.MIT.EDU
> Subject:      Re: "Item not covered by a release strategy"
>
> Hi Neeraja -
>
> Thank you for the idea, but authorizations don't seem to be the problem.  We have that authorization object and value in the requisitioner's profile already, and an SU53 after creating a PR line (which doesn't get covered by a release strategy) shows that "All authorization checks have so far been successful"...
>
> Any other ideas?  Anybody?
>
> Regards,
> Sherman
>
>
> "Sheth, Neeraja" wrote:
>
> > Sherman
> >
> > When we upgraded from 3.1I to 4.6C, no release strategy would get assigned to the new PRs. We found that we needed additional authorization : authorization for class type C_TCLA_BKA,  class type 32. We have added this authorization to the general SAP user profile so everyone has it. This resolved the issue for us.
> >
> > Try executing SU53 immediately after creating a new PR line item.
> >
> > Regards
> >
> > Neeraja
> >
> > > -----Original Message-----
> > > From: Sherman S. Wright [SMTP:swright at lsil.com]
> > > Sent: Tuesday, July 10, 2001 4:31 PM
> > > To:   SAP-WUG at MITVMA.MIT.EDU
> > > Subject:      "Item not covered by a release strategy"
> > >
> > > Hi All -
> > >
> > > I wonder if anyone's had a problem similar to this:
> > >
> > > We use release strategies for our Purchase Requisition lines, and all
> > > has been working fine, across our complete landscape (DEV, QA, PRD),
> > > which are all 4.6B.  However, a few weeks ago, our DEV box was
> > > "upgraded" to Support Package 28 (it was at 25 prior to that), and now
> > > all of our PR lines get the message "Item ##### not covered by a release
> > > strategy".  Everything seems to be configured the same as the other
> > > clients, workflow verification is correct, all classifications are
> > > maintained, and "old" PRs will continue through workflow, but nothing
> > > new is covered by a release strategy.
> > >
> > > Any ideas?
> > >
> > > Regards,
> > > Sherman << File: Card for Sherman S. Wright >>
 