Event Linkage Keeps Deactivating

George J. Campbell-Kelly george.campbell-kelly at nstarch.com
Tue Oct 10 04:02:18 EDT 2000


I often get this when transporting workflows.
 
Cannot rember exactly how to cure it, but I always try simulating the
event, and doing an extended error check on the whole workflow and its
tasks. This usually helps me find the error and correct it. Also check the
bindings on the event linkage, and its entry is the event linkage tables.
 
How this helps/reassures you,
 
George
 
 
 
 
 
 
 
SIMON ORCHARD <ORCHARDS at gkn-whl.co.uk> on 10/10/2000 08:52:07
 
Please respond to "SAP Workflow Users' Group" <SAP-WUG at MITVMA.MIT.EDU>
 
To:   SAP-WUG at MITVMA.MIT.EDU
cc:    (bcc: George Campbell-Kelly/GB/NSC/ICI)
Subject:  Event Linkage Keeps Deactivating
 
 
 
 
All,
 
I have a live workflow in which one task event linkage keeps deactivating.
Recently it looks as though it deactivates each time it is called, however,
so far I haven't been able to prove this in every case. Does anybody have
any ideas why this would happen. Whenever I check the task binding, the
consistency check is OK. The entry for the task in table SWETYPECOU always
exists.
 
Also, when I activate the task I get an SAP error message "Type linkage
between <OBJECT TYPE> <EVENT> and <TASK>: Insertion not possible". However
when I return to the Event Simulation screen the task event linkage is then
activated.
 
Any Ideas?
 
Thanks in advance,
 
Simon Orchard
Business Analyst, Information Systems
GKN Westland Helicopters Ltd.
 
 
 
 
 
 
 
IMPORTANT NOTICE:
This email is confidential, may be legally privileged, and is for the
intended recipient only.  Access, disclosure, copying, distribution, or
reliance on any of it by anyone else is prohibited and may be a criminal
offence.  Please delete if obtained in error and email confirmation to the
sender.
 


More information about the SAP-WUG mailing list