Regarding wait step

Paul.Bakker@osr.treasury.qld.gov.au Paul.Bakker at osr.treasury.qld.gov.au
Wed May 26 00:00:33 EDT 2010


Joe K,

You should use 'workflow events' in situations like this. You are waiting
for a specific situation - ie when all transport requests are released.

Putting in long-running 'wait' loops is not best practice...

cheers
Paul B



                                                                           
             joe kirubagaran                                               
             <joekirubagaran at g                                             
             mail.com>                                                  To 
             Sent by:                  "SAP Workflow Users' Group"         
             sap-wug-bounces at m         <sap-wug at mit.edu>                   
             it.edu                                                     cc 
                                                                           
                                                                   Subject 
             26/05/2010 01:53          Regarding wait step                 
             PM                                                            
                                                                           
                                                                           
             Please respond to                                             
               "SAP Workflow                                               
               Users' Group"                                               
             <sap-wug at mit.edu>                                             
                                                                           
                                                                           




Hi Everyone,

I have a requirement like when the tasks of the particular transport
request is released i need to trigger a mail to basis people to relase the
transport request. For this i have formed a fm that checks whether the
tasks are released r not . I have this fm in a do-enddo statement
i.e.,until all the tasks are released it will keep on checking it. I have
this fm in a method of a class and is used in the activity step of my work
flow....so now my doubt is a whether there will be any performance issue
due to this activity step that enforces wait .......I mean the step may
take a day r a week to complete...so will there be any issue......

Thanks & Regards,
Joe._______________________________________________
SAP-WUG mailing list
SAP-WUG at mit.edu
http://mailman.mit.edu/mailman/listinfo/sap-wug



******************************************************************************************************************************************************

Only an individual or entity who is intended to be a recipient of this e-mail may access or use the information contained in this e-mail or any of its attachments.  Opinions contained in this e-mail or any of its attachments do not necessarily reflect the opinions of Queensland Treasury.

The contents of this e-mail and any attachments are confidential and may be legally privileged and the subject of copyright.  If you have received this e-mail in error, please notify Queensland Treasury immediately and erase all copies of the e-mail and the attachments.  Queensland Treasury uses virus scanning software.  However, it is not liable for viruses present in this e-mail or in any attachment.  

******************************************************************************************************************************************************




More information about the SAP-WUG mailing list