On Thursday 10 April 2008 12:11:02 Christian Wallner wrote:
> Hi WUGers!
>
> I have a question which I'm sure is easy to answer for some guys here:
> I want a workflow to terminate itself after n hours because its obsolete
> then. Basically the wf is quite simple, it consists of a parallel section
> with 4 branches (1 out of 4 to complete). So my first thought was a wait
> event in a 5th branch. But unfortunately I didn't find out how to tell
> this step to terminate itself after wf creation date+n hours.
>
> Any ideas?
Already answered, but it seems everyone wants that fifth branch. In your case 
it is not really necessary, but you may still want one to make the reporting 
easier if you have any. However, you *could* simply define a Latest End 
deadine on any of the four steps you already have active and terminate the 
workflow that way (this will be a modelled deadline of course).
-- 
Kjetil Kilhavn (+47 40220607)