Work Items in are 'In Process'

Munday,Sherie J. MUNDAYSJ at airproducts.com
Mon May 22 10:55:19 EDT 2006


Alon,
We have had similar experiences with workitems getting "stuck" for no
apparent reason since our upgrade to ECC 5.0.  We opened an OSS note,
and were told to apply Note 924388.  Unfortunately our client was
refreshed and I cannot recreate the problem, so I have to wait to be
able to test to see if applying the note will work.  Maybe it will work
for you.
Best of Luck,
Sherie
 
Sherie Munday
Workflow Developer/Analyst
Air Products & Chemicals, Inc.

  _____  

From: sap-wug-bounces at mit.edu [mailto:sap-wug-bounces at mit.edu] On Behalf
Of Alon Raskin
Sent: Monday, May 22, 2006 8:45 AM
To: SAP Workflow Users' Group
Subject: RE: Work Items in are 'In Process'


Hi Hans,

Thank you for the response.
 
I know why the work item is 'stuck'. That is not my question.
What I was wondering about is why the work item status is still 'In
Process'? I would have expect SWWERRE to change it to ERROR by now. 

Regards,
 
Alon Raskin
e: araskin at 3i-consulting.com <mailto:araskin at 3i-consulting.com> 
p: +1 207 409 4983
 

  _____  

From: sap-wug-bounces at mit.edu on behalf of Brilleman JOHANNES
Sent: Mon 5/22/2006 08:45
To: SAP Workflow Users' Group
Subject: RE: Work Items in are 'In Process'


  _____  

Notice of Disclaimer: Please note that this e-mail, and the contents
thereof, is subject to the Standard PetroSA e-mail Disclaimer which is
located at http://www.petrosa.com/Content/380.html 
  _____  

Hi Alon,
 
please have a look on the dump log (ST22) of 4 days ago and check if
that workitem did not produce a short dump.
 
Regards,
 
Hans

	-----Original Message-----
	From: sap-wug-bounces at mit.edu [mailto:sap-wug-bounces at mit.edu]On
Behalf Of Alon Raskin
	Sent: Monday, May 22, 2006 2:22 PM
	To: sap-wug at mit.edu
	Subject: Work Items in are 'In Process'
	
	
	We have some work item in Production that have been 'In Process'
for about 4 days now. I expected that they would have gone into ERROR
status by now. Batch job SWWERRE is scheduled and running periodically.
	 
	Is this an OSS or are we missing some configuration somewhere?
	
	Regards,
	 
	
	
	
	Alon Raskin
	e: araskin at 3i-consulting.com <mailto:araskin at 3i-consulting.com> 
	p: +1 207 409 4983

The information contained in this electronic message and any attachments
to this message are intended for the exclusive use of the addressee(s)
and may contain proprietary, confidential or privileged information. If
you are not the intended recipient, you should not disseminate,
distribute or copy this e-mail. Please notify the sender immediately and
destroy all copies of this message and any attachments. 

WARNING: Computer viruses can be transmitted via email. The recipient
should check this email and any attachments for the presence of viruses.
The company accepts no liability for any damage caused by any virus
transmitted by this email.

www.wipro.com
	

  _____  

The Petroleum Oil & Gas Corporation of South Africa (Pty) Ltd 
trading as "PetroSA" Reg. No. 1970/008130/07. 
 
Directors: 
 
Dr P S Molefe (Chairman)
 
Mr S Mkhize (President and Chief Executive Officer),
 
Mr N G Nika (Executive), Mr A R Nkuhlu, Ms R J Huntley, Ms T C P
Chikane,
 
Mr N H Gumede, Prof B Figaji, Mr A W Mjekula, Mr T O Mokwena,
 
Mr M B Damane, Ms P S V Ngaba (Company Secretary)
 
 
  _____  

-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://mailman.mit.edu/pipermail/sap-wug/attachments/20060522/44aaeb3b/attachment.htm


More information about the SAP-WUG mailing list