Workitem delegation
Michael Marten
michael.marten at philips.com
Thu May 26 10:02:55 EDT 2005
Hello,
just a short idea: don't delete org. unit 1, make sub. units real "sub
organiszational units".
But I guess this is not the expected solution ...
old situation
org. unit 1 (don't delete it)
=> useridX
=> useridY
=> useridD
. => useridE
new situation
org. unit 1 (don't delete it)
=> sub org A
=> useridX
=> useridY
=> sub org A
=> useridD
. => useridE
Michael - and yes, here in Hamburg the sun is shining!
"Maes Steven"
Sent by:
sap-wug-bounces at mit.edu
26.05.2005 15:35
Please respond to
"SAP Workflow Users' Group" <sap-wug at mit.edu>
To
<sap-wug at mit.edu>
cc
Subject
Workitem delegation
Classification
Dear all,
I have a question regarding the assignment of work items to the org.
structure.
Let’s assume that certain work items were assigned to org. unit 1.
The customer decided to divide this unit into 2 sub org. units.
No problem so far. We changed the workflow templates and the new work
items are assigned to the correct organisational unit.
Problems arise when we look at the work items from the past. These are
still assigned to the original org unit.
We would like to re-assign these items to the new org units.
Is there anyone who has an idea for solving this issue ? (Program,
function, etc…)
Thanks in advance,
Steven Maes
Stymatic Consulting
_______________________________________________
SAP-WUG mailing list
SAP-WUG at mit.edu
http://mailman.mit.edu/mailman/listinfo/sap-wug
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://mailman.mit.edu/pipermail/sap-wug/attachments/20050526/cd0d5e11/attachment.htm
More information about the SAP-WUG
mailing list