Strange Deadline Problems
Sue Keohan
keohan at ll.mit.edu
Thu Dec 8 19:52:30 EST 2005
Hi Mike,
Well, sorry that wasn't your problem. But hopefully someone else won't
make the same mistake I did.
Cheers,
Sue
Mike.Nickson at bhint.com wrote:
>
> Sue
>
> Thanks for the response, but this is not the case here as the SWWWDHEX
> job has continued to run as scheduled.
>
> Mike
>
>
>
>
> *"Susan R. Keohan" <keohan at ll.mit.edu>*
> Sent by: sap-wug-bounces at mit.edu
>
> 07/12/2005 21:50
> Please respond to "SAP Workflow Users' Group"
>
>
> To: "SAP Workflow Users' Group" <sap-wug at mit.edu>
> cc:
> Subject: Re: Strange Deadline Problems
>
>
>
>
> Mike,
>
> Check how RSWWDHEX was running. We had an issue where the job stopped
> resubmitting itself due to
> system contraints. Then it did not run for several months... When we
> realized that RSWWDHEX was not
> running, we kicked it off (NOTE TO ALL< YOU PROBABLY DON"T WANT TO DO
> THIS). All the deadline
> messages that had been waiting in the queue got sent.
>
> There is an OSS Note to get around this kind of scheduling conflict,
> but I forget the #.
>
> Cheers
> Sue
>
> Mike.Nickson at bhint.com wrote:
>
> >
> > We are suddenly experiencing strange deadline problems here where
> > deadlines are being invoked for workflows that have completed.
> >
> > In our leave request workflow, we generate an email reminder if the
> > employee's line manager has not actioned the workitem within 5 days,
> and
> > if unactioned after 15 days then we generate a second email.
> >
> > We have instances of a leave request workflow that has been authorised
> > and the workflow has completed within the 5 days without any deadlines
> > being invoked.
> >
> > Inexplicably the deadline emails (both 5 and 15 days) were generated
> > last night . . . . even though the workflow completed on the 14th
> > November !
> >
> > I see that there is an entry in SWWWIDEADL for the workitem, and
> > presumably it is this that is being picked up by RSWWDHEX.
> >
> > I would expect that the SWWWIDEADL entry for a workitem would be
> removed
> > when a workflow completes, but this does not seem to be the case.
> >
> > Any one experienced this type of phenomena before ?
> >
> > Yours Confusedly.
> >
> > Mike
> >
> > SAP HR version 4.70 level 43
> >
> >
> > ------------------------------------------------------------------------
> >
> > _______________________________________________
> > SAP-WUG mailing list
> > SAP-WUG at mit.edu
> > http://mailman.mit.edu/mailman/listinfo/sap-wug
>
> --
> Susan R. Keohan
> SAP Workflow Developer
> MIT Lincoln Laboratory
> 244 Wood Street
> LI-200
> Lexington, MA. 02420
> 781-981-3561
> keohan at ll.mit.edu
> _______________________________________________
> SAP-WUG mailing list
> SAP-WUG at mit.edu
> http://mailman.mit.edu/mailman/listinfo/sap-wug
>
>
>------------------------------------------------------------------------
>