Task requested end

Martijn Wever martijn.wever at eozen.com
Mon Apr 11 07:24:31 EDT 2005


Hi Eric,

That's why you can use 'Expression' as reference:
1. Take the begin-of-leave date from the business object (one of the
attributes)
2. subtract two days
3. Put container element containing calculated value in the deadline 'date'
field.

I think it is possible to subtract days from a date field using a container
operation. If not build a method or virtual attribute.
Also make sure the calculated date can never be in the past because this
causes errors.
 
Met vriendelijke groet / Regards,
 
Martijn Wever

-----Original Message-----
From: sap-wug-bounces at mit.edu [mailto:sap-wug-bounces at mit.edu] On Behalf Of
Caillet, Eric
Sent: Monday, April 11, 2005 11:53
To: ''SAP Workflow Users' Group' '
Subject: Task requested end

Hi all,

i must develop a specific workflow for leave request (specific process) but
i've a problem for modeling deadline task. 

Well, the employee create the leave request by Web, the workflow is started.
The manager has up to 2 days before the beginning of the absence to validate
or refuse the absence. My problem is for modeling this process, because in
SAP task the deadline reference date is "Work item creation" or "Workflow
creation", the ideal would have been to input a date of reference (beginning
of the absence), but i can't do that. Any ideas ?

Thanks so much for help.

Best regards,

This e-mail and any attachment is for authorised use by the intended
recipient(s) only. It may contain proprietary material, confidential
information and/or be subject to legal privilege. It should not be copied,
disclosed to, retained or used by, any other party. If you are not an
intended recipient then please promptly delete this e-mail and any
attachment and all copies and inform the sender. Thank you.
_______________________________________________
SAP-WUG mailing list
SAP-WUG at mit.edu
http://mailman.mit.edu/mailman/listinfo/sap-wug




More information about the SAP-WUG mailing list