Possibly the tRFC failed and an entry was created in SM58. Then the
report (I forget its name) ran and redlivered the 'errored' rfc.=20
 
 
Alon Raskin
e: araskin at 3i-consulting.com
w: http://www.3i-consulting.com
 
-----Original Message-----
From: SAP Workflow [mailto:Owner-SAP-WUG at MITVMA.MIT.EDU] On Behalf Of
Kevin Wilson
Sent: 02 November 2004 17:55
To: SAP-WUG at MITVMA.MIT.EDU
Subject: Deadline sent a little late
 
We just had an isolated incident with a deadline being sent 12 minutes
after the time it was supposed to be sent. The entry in the deadline
table showed 13:33. The batch job (scheduled every 5 minutes) ran at
13:35 and 13:40 without picking it up but the 13:45 job picked it up and
processed it. Has anyone encountered a similar occurrence? What could
cause the job to not process a deadline passed entry?
 
Thanks
Kevin
 