EBP work item remains after execution

Nicholas Brand nicholas.n.brand at uk.ibm.com
Tue May 25 05:04:13 EDT 2004


Hmmm...I thought there might be complications.
 
Given the time constraints I'll recommend that we bring the business
process in line with the standard confirmation approval workflow rather
than develop a web transaction with workflow handling code.
 
Thank you again Jocelyn.
 
 
Kind regards,
Nicholas Brand
 
 
 
 
 
 
             "Dart, Jocelyn"
             <jocelyn.dart at sap
             .com>                                                      To
             Sent by: SAP              SAP-WUG at MITVMA.MIT.EDU
             Workflow                                                   cc
             <Owner-SAP-WUG at MI
             TVMA.MIT.EDU>                                         Subject
                                       Re: EBP work item remains after
                                       execution
             25/05/2004 04:39
 
 
             Please respond to
               "SAP Workflow
               Users' Group"
 
 
 
 
 
 
Hi Nicholas,
This will not work for EBP.
EBP has special workflow handling around it to cater for the closing of
work items.
BBPCF02 won't expect to deal with work items and therefore won't call the
relevant handling.
BUS2203.SAVED event won't work as you are dealing with a creation scenario
- so the event has
to be raised with a special function to pass back the calling work item.
 
You could try using one of the BADIs e.g. the DOC SAVE BADI to complete the
work item perhaps using a WAPI.
Can't guarantee anything though.
Jocelyn
 
-----Original Message-----
From: SAP Workflow [mailto:Owner-SAP-WUG at MITVMA.MIT.EDU] On Behalf Of
Nicholas Brand
Sent: Tuesday,25 May 2004 12:58 AM
To: SAP-WUG at MITVMA.MIT.EDU
Subject: EBP work item remains after execution
 
 
Hello,
 
We're using EBP v3.5.
 
I've created a new task that uses the FORM.HTMLPROCESS method.
I've assigned the web transaction BBPCF02 (Confirm Goods Receipt or
Service) to the task via Goto > Web transaction
 
When I execute the new workitem it works - I go into the create
confirmation screen (BBPCF02), select the relevant PO and create a new
confirmation against it.
When I save the confirmation, I get a message that the confirmation has
been created; however when I return to the inbox, the workitem is still
there.
 
Initially I had no 'Confirm end if processing' or terminating event set.
Then I tried 'Confirm end of processing' - doesn't seem to work with
WebGUI.
Then I tried using a terminating event based on the BUS2203.Saved event of
the new confirmation - also doesn't work.
 
Any other suggestions I could try?
 
 
Kind regards,
Nicholas
 


More information about the SAP-WUG mailing list