Background step to set a project system status

ezra saarell at netvision.net.il
Wed Mar 17 03:53:54 EST 2004


Hello,
I need to create a background step which set's a system status for a project definition.
It is mainly used to set the status TECO for the project, I need the step to do the same thing as when setting status TECO in the PS (CJ20N),
which means setting the status TECO to all entities in the project's hierarchy (Project definition, WBSs, Networks...  ).
 
Does anyone know a BAPI or a standard function\method that does such a thing ?
 
Thanks you,
Elad.
 