Material Master WF

"Lücking, Claus" clucking at danfoss.com
Wed Sep 3 02:37:43 EDT 2003


Hi Thad.
 
Yes, the maintenance status is a possible solution. I check on this in =
a
start condition of a material master WF.
 
Claus L=FCcking.
 
-----Original Message-----
From: Thaddeus.Gorbal at pb.com [mailto:Thaddeus.Gorbal at pb.com]=20
Sent: 3. september 2003 01:13
To: SAP-WUG at MITVMA.MIT.EDU
Subject: Material Master WF
 
 
Hello All:
 
I have a request to build a material master workflow which would =
control
creation of appropriate views by appropriate agents.
 
Material creation/extension requests are fed to SAP form an outside =
system
via Idoc/Ale. The event BUS1001006.Created seems to be good for =
material
creation request, but it is not raised for the material extensions to =
other
plants.
 
I have been considering using just the BUS1001006.VIEWCREATED event to
trigger my WF.  However, I am not quite sure how to control starting
workflow, since multiple such events are raised at the new material =
request
as well as the extension of one.
 
Your hints and tips would be very appreciated. It looks like the =
maintenance
status could be useful.
 
 
Thanks in advance,
Thad Gorbal
Voyager WF Development and Administration
 


More information about the SAP-WUG mailing list