All,
I have a step that has a requested start of nine minutes after the Work item
is created. However, the actual start is always 10 minutes. When I look in
the log, it says requested start is 9 minutes after the work item creation
time but the actual start is 10 minutes after the creation time. Is 10
minutes the minimum delay I can have or am I doing anything wrong. I am on a
46B system.
 
 
Thanks
Swami
 