Dialog Workitem with many agents

Phillips, Tim Tim.Phillips at ser.com
Fri Oct 25 09:48:51 EDT 2002


Hi Angelo,
 
SAP is meant to work that way.
 
The normal way around it is to remind the agents to 'replace' the workitem
if they do not plan, or are unable, to complete its execution.
 
Regards,
 
Tim
 
-----Original Message-----
From: Angelo Besenzoni [mailto:"Angelo
Besenzoni/SAP_CONSULTING%SAP_CONSULTING"@mailnotes.ibm.it]
Sent: 25 October 2002 10:41
To: SAP-WUG at MITVMA.MIT.EDU
Subject: Dialog Workitem with many agents
 
 
Hello folks !
 
Hope you can help me.
 
Our system is on release 4.5B
 
We have an object method with dialog, not synchronous; its relevant task is
with
a terminating event.
 
In the workflow, the agent is assigned to the task by an expression whose
value
is a position of an organizational unit.
Generally, in that position we have different users (more than one).
Everything works well, all the users have the workitem in their Outlook (we
use
Sap-Mapi).
 
Unfortunately, when a user executes the workitem, but doesn't terminate it
(that
is, the terminating event isn't activated) because for example he/she ends
the
task without to save, this user becomes the only owner of the workitem and
in
the Inbox of the other users the workitem disappears... so only the first
user
who executes the workitem for the first time, can later on execute the
workitem
and terminate the task..
 
How we can do to hold the workitem in all the users Inbox until someone
terminates it???
 
Any help is greatly appreciated.
 
Thanks.
Angelo
 
 
Angelo Besenzoni
Sap Italia Consulting s.r.l.
tel. +39 3351357236
 


More information about the SAP-WUG mailing list