You need to reconsider the process. If user A has not saved the data, how is
his superior (possibly the next day) going to see it?
 
The main options are:
- use of material statuses to prevent the data from being used productively
before it's approved by the superior (still, you get a material created,
which could be a duplicate of an existing one)
- collecting material information in some request form that would be
approved by the superviser and then copied into the material master (which
is OK, but means more development)
 
There are many variations around this, but you need to decide on the general
approach first.
 
Kind regards,
Tomasz
 
-----Original Message-----
From: Ravi Govind [mailto:pgm7070 at yahoo.co.in]
Sent: Saturday, May 11, 2002 6:43 PM
To: SAP-WUG at MITVMA.MIT.EDU
Subject: Material Master Workflow
 
 
Hi to all,
 
I have the following scenario,will you please throw
some light on this.
 
User will create material master record, before
saving, it should be approved by superior.
 
Can you please suggest some thoughts on this.
 
Thanks in advance,
 
Srini B
 
________________________________________________________________________
Everything you always wanted to know about cars and bikes,now
 at: http://in.autos.yahoo.com/cricket/tracker.html
 


More information about the SAP-WUG mailing list