Can't create Event PurchaseRequisition.significantlyChanged
Josef Herwig
josef.herwig at gmx.de
Thu Jun 20 05:59:15 EDT 2002
Hi Experts,
i have a little problem in our 4.5B System with creating the event
PurchaseRequisition.significantlyChanged by changing the purchase requisiton.
i've made the following entries in the purchase requisition customizing:
Release Procedure --> Set Up Procedure with Classification
Release indicator = G
changes after start process:
changeability = 4
value chgs. = 10,0 percent
if these parameters set a message should be shown if you change the price or
the quantity of an item in the requisition. but it doesn't works
the event PurchaseRequisition.significantlyChanged is enabled
note: 0497928 is already maintained
Do you have any ideas?
Thanks Josef
--