Hi Assy,
We want to implement a workflow solution for the Material master change.
Different options are:
1. Use MM12 for scheduling the changes and trigger the workflow to check for
field dependencies(Example: Material group has dependency on Profit centre
and product hierarcy) and activate the changes using MM13.
2. Use a custom form to capture most of the key fields to be changed and
route the form based on the dependency check. Based on the valid from date,
the change will be immediate(MM02) or scheculed(MM12).
3. Use Engineering Change Management?
Please advice.
Thanks
Ram
> -----Original Message-----
>> From: ASSY, SOSTHENE [SMTP:S.ASSY at AFDB.ORG]
> Sent: Wednesday, November 28, 2001 7:02 AM
> To: SAP-WUG at MITVMA.MIT.EDU
> Subject: Re: Material Change Workflow
>
> Hi Ram
>
> Do you want to trigger a workflow some data changed ?
> Please be more explicit
>
> Mr. Sosthene Assy
> African Development Bank
> S.ASSY at AFDB.ORG
> Tel : 20-20-53-03
>
> > -----Original Message-----
> > From: Chintamaneni,Rammohan,GLENDALE, IS
> > [SMTP:rammohan.chintamaneni at us.nestle.com]
> > Sent: Tuesday 27 November 2001 19:24
> > To: SAP-WUG at MITVMA.MIT.EDU
> > Subject: Material Change Workflow
> >
> > Hi,
> > Did anyone worked on Material Master Change Workflow?
> >