Mass change/retirement workflow
R Tannert
tnn at ornl.gov
Thu Aug 17 13:05:44 EDT 2000
Tony,
Sorry I missed your original message. I encountered the same problem when
we upgraded from 3.1H to 4.0B. I sent an OSS message and got the following
response:
Hello Rob,
in 4.0 WS25 was enlarged and treats now bulk changes and retirements
with and w/o revenue. So WS24 became superfluous and was deleted. Use
WS25 instead (disable the event linkage from AM_AI CREATED to WS24 and
enable - or create - the event linkage to WS25).
Kind regards,
Ingo Severing, development support FI-AA
Rob
>Jeff,
>
>Thanks for the reply. I never did receive any answers. However, I did figure
>out an alternative solution. We have completely abandoned the WS24
>workflow and
>have implemented the WS25 instead. I found it fairly odd that the WS24
>definition did not make it into our upgraded (4.6C) system but the event
>linkage
>(SWE2 entry) did. I could simulate the event AM_AI, CREATED and WS24
>would show
>up as a workflow to be started but I couldn't use it because the
>definition was
>not available. I guess SAP has abandoned the WS24 workflow as well?
>
>After working with the functional folks I believe WS25 will meet our
>needs. We
>have run some tests in our development system with successful mass asset
>retirements and changes.
>
>Tony Gramelspacher
>SSC
>(314) 589-7996
>