[Olympus] OLYMPUS Schedule/Crane Activities

Uwe Schneekloth uwe.schneekloth at desy.de
Thu Jul 28 06:28:12 EDT 2011


Dear Colleagues,

Here is an update of the crane status and the schedule:

The crane will not be ready on Friday. The motor will be back some time on
Monday, will then be installed and checked out. We shifted some activities
and tried to do items scheduled for next week.

The modification of the interlock system and power off button is being finished
right now. This afternoon (13:00 - 18:00 hrs) the tunnel will be closed in order
to perform the interlock pre-tests. 
Temporary (key) access will be possible after about 18:00hrs.

Tomorrow the tunnel will be closed (interlock set) from 7:00 to about 18:00 hrs
for power supply test of the DORIS magnets and the test of our magnet starting
at 10:00 hrs.

On Monday, we will try to close the sub-detector frame again. This should work now
after the modification of the target support (stiffening bars underneath the box
beams). We will then open the main detector frame.
The ceiling will hopefully be closed Monday afternoon.

The survey is now scheduled to start on Tuesday.

Best regards,
Uwe


_____________________________________________________
|                                        
| Dr. Uwe Schneekloth   
| OLYMPUS                                           
| Deutsches Elektronensynchrotron  
| Notkestrasse 85                                     
| D-22603 Hamburg/Germany              
| Tel: +49-40-8998 2007  Fax: +49-40-8998 3092 
| email: uwe.schneekloth at desy.de                          
_____________________________________________________

On 22.07.2011, at 11:05, Uwe Schneekloth wrote:

> Dear Colleagues,
> 
> The 40ton crane in the DORIS is unfortunately defective again. The motor has
> to be sent to the company for repair. This will take until end of next week.
> Next week we will try to do some tasks which were scheduled  for the following
> week.
> 
> A rough schedule for next week is:
> 
> - Finish the water cooling of the toroid
> - Mount the missing support for moving the north half of the detector frame 
> - Close the detector main frames
> - Complete the interlock system
> - Do as much of the interlock tests as possible
> - Commission the toroid power supply
> - Power up the toroid
> - Install the Moller support and tables
> - Start technical commissioning of DORIS as possible
> 
> We expect that the concrete ceiling can be installed end of the week, if the
> repair goes fast, or on the weekend.
> After this the target system and the detector will be surveyed.
> 
> The internal survey of the Moller system can now be done early next week.
> 
> Best regards,
> Uwe
> 
> _____________________________________________________
> |                                        
> | Dr. Uwe Schneekloth   
> | OLYMPUS                                           
> | Deutsches Elektronensynchrotron  
> | Notkestrasse 85                                     
> | D-22603 Hamburg/Germany              
> | Tel: +49-40-8998 2007  Fax: +49-40-8998 3092 
> | email: uwe.schneekloth at desy.de                          
> _____________________________________________________
> 