[Tang-Residents] Bldgs. W71/W84/W85 Steam, Building Heat, and Domestic Hot Water Shutdown (#24069)
Michael J Collins
collinsm at mit.edu
Thu Aug 8 14:44:25 EDT 2024
Facilities Repair completed.
Steam is now returning back to buildings
On Aug 7, 2024, at 5:57 PM, Michael J Collins <collinsm at mit.edu> wrote:
Gentle reminder for tomorrow. NO HOT WATER 9am to 2:00pm
Please plan accordingly
From: Michael J Collins
Sent: Monday, August 5, 2024 7:10 AM
To: tang-residents <tang-residents at mit.edu>; westgate-official <westgate-official at mit.edu>
Subject: FW: Bldgs. W71/W84/W85 Steam, Building Heat, and Domestic Hot Water Shutdown (#24069)
Please see the hot water shut down scheduled for this Thursday 8/8/24
Subject: Bldgs. W71/W84/W85 Steam, Building Heat, and Domestic Hot Water Shutdown (#24069)
Importance: High
Type: Normal
Date: August 8, 2024
Day: Thursday
Time: 9:00 AM-2:00 PM
Building(s): W71, W84, and W85
Room(s): All
System: Domestic Hot Water, Heating Hot Water, High Pressure Steam, Medium Pressure Steam, Low Pressure Steam
Duration: 5 hrs.
Reason:
Repair Steam line anchor in MH 1021
Effect:
Domestic Hot Water, Heating Hot Water, High Pressure Steam, Medium Pressure Steam, Low Pressure Steam
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://mailman.mit.edu/pipermail/tang-residents/attachments/20240808/bc07b870/attachment.htm>
More information about the Tang-Residents
mailing list