Dear colleagues,
The week of June 21, work is scheduled to commence to renovate Building W91. The project will begin with the installation of a fence around the building. Work hours are weekdays from 7AM-4PM. Some noise is anticipated. Building W91 is expected to reopen for occupancy in late January 2022.
Traffic will increase in the area as construction vehicles enter and exit the site from Audrey Street and Amesbury Street throughout the day. Signage to direct pedestrians and traffic will be posted. Notifications of upcoming construction activities will be shared as this project proceeds. See the attached map for the location of work.
Questions about this work may be directed to Gerhard Sinani (sinanig at mit.edu; 617-233-1413) or Thanh Nguyen (thanhn at mit.edu; 617-291-7806).
Please share this information with individuals in your area who may be impacted by this work.
Regards,
Laurie
Laurie Verner
Communications Coordinator
MIT Department of Facilities
Visit the construction updates page of the Facilities site for information on this and other activities:
http://web.mit.edu/facilities/construction/updates.shtml
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://mailman.mit.edu/pipermail/tang-residents/attachments/20210617/6aa0580d/attachment.html
-------------- next part --------------
A non-text attachment was scrubbed...
Name: W91 renovation.pdf
Type: application/octet-stream
Size: 3661293 bytes
Desc: W91 renovation.pdf
Url : http://mailman.mit.edu/pipermail/tang-residents/attachments/20210617/6aa0580d/attachment.obj
More information about the Tang-Residents
mailing list