Manually Activate/Deactivate WF Event Linkage in Non Modifiable System (e.g. Production) without a transport
Edward Diehl
edwarddiehl at hotmail.com
Thu Sep 8 15:12:44 EDT 2011
Sheldon,
If you go to the Additional Data for the workflow template and select Agent Assignment>Maintain and select Attributes, along with General Task, etc. you will see a check box at the bottom "Locked for Instantiation."
That will prevent the workflow from starting. Same effect as turning off the event linkage, right?
Ed
> Subject: Manually Activate/Deactivate WF Event Linkage in Non Modifiable System (e.g. Production) without a transport
> To: sap-wug at mit.edu
> From: soxenber at csc.com
> Date: Thu, 8 Sep 2011 14:53:01 -0400
>
>
> In ECC 6.0 Basis Release 700, I can manually Activate/Deactivate a WF Event
> Linkage in a Non Modifiable System (e.g. Production) without a transport.
> In ECC 6.0 Basis Release 702, I cannot manually Activate/Deactivate a WF
> Event Linkage in a Non Modifiable System (e.g. Production).
>
> Is there an ECC 6.0 Basis Release 702 config that permits manual
> Activate/Deactivate of a WF Event Linkage in a Non Modifiable System (e.g.
> Production)?
> Otherwise if a transport is required (not useful in an emergency), is there
> a WF Administrator utility/function to Activate/Deactivate a WF Event
> Linkage in Prod?
>
> Thank you very much.
>
> SHELDON OXENBERG
> System Architect Principal Leader
> LMP Technical Architect, SAP Workflow
> CSC
>
> _______________________________________________
> SAP-WUG mailing list
> SAP-WUG at mit.edu
> http://mailman.mit.edu/mailman/listinfo/sap-wug
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://mailman.mit.edu/pipermail/sap-wug/attachments/20110908/c4c4998e/attachment.htm
More information about the SAP-WUG
mailing list