Deadlines based on factory calendar - is The Book wrong?

Soady, Phil phil.soady at sap.com
Thu Sep 28 05:11:50 EDT 2006


Hi  Kjetil,
I think you have hit the nail on the head and this is why Paul
correctly believes the sample solutions are  wrong (don't address his
issue).

The sample solutions only convert a calculated date into a working day.
They do not calculate an offset of x working days from now.

The only way to do this is to call the calendar test x times for each
day
from now until the number of days tested as positive as as work days
equals the desired offset.

The sample solutions simply correct a date to next factory calendar
date.
That's my quick interpretation of the code at least.

I have also seen this logic mistake around factory calendar in other
custom code stretches.

ie incorrect.
today (t) + offset (n) = y.
corrected date (df) = factory_cal( y).
df is now = to y or higher to reach first working after y.

However this is flawed, since Y is not (n) working days more than (t).
A loop to call the calendar check (n) times is required.

Cheers
Phil.


Phil Soady 
Solution Architect 
Netweaver Consulting 
SAP Australia 
M  +61 412 213 079 
F  +61 2 9957 7263 
mailto:phil.soady at sap.com 


-----Original Message-----
From: sap-wug-bounces at mit.edu [mailto:sap-wug-bounces at mit.edu] On Behalf
Of Kjetil Kilhavn
Sent: Thursday, 28 September 2006 6:31 PM
To: SAP Workflow Users' Group
Subject: RE: Deadlines based on factory calendar - is The Book wrong?

Hmmmm... I looked a little more at the code in the presentation
(embedded text file), and it looks like it is exactly the same solution
as the appendix in the book.

However, there is one thing that makes me wonder about your requirement.
You say that not only should the deadline be a working day, but only
working days should be taken into account. It may make some sense for
very short deadlines, e.g. a two-day deadline, but should a 15-day
deadline be a three-week deadline? In the worst case (I don't know what
options the standard function modules give you) you will have to loop
over every date in the range and check if it is a working day or not.
-- 
Kjetil Kilhavn, Statoil OFT GBS BAS DEV SAP
 

> -----Original Message-----
> From: Kjetil Kilhavn 
> Sent: 28. september 2006 10:14
> To: 'SAP Workflow Users' Group'
> Subject: RE: Deadlines based on factory calendar - is The Book wrong?
> 
> I think this has been discussed several times before (have 
> you searched the archives?) in this group, but I can't recall 
> if anyone has had quite the same requirements as you. 
> 
> I have attached a PDF file (can't remember where I got it, 
> whether it was in this group or perhaps on ASUG's site) with 
> another implementation, and a PowerPoint file with an 
> implementation that seems to be exactly what you want.
> 
> If you find none of these match your needs than please create 
> the ultimate solution and share it with the rest of us.
> --
> Kjetil Kilhavn, Statoil OFT GBS BAS DEV SAP
>  
> 
> > -----Original Message-----
> > From: sap-wug-bounces at mit.edu 
> > [mailto:sap-wug-bounces at mit.edu] On Behalf Of 
> > Paul.Bakker at osr.treasury.qld.gov.au
> > Sent: 28. september 2006 09:13
> > To: sap-wug at mit.edu
> > Subject: Deadlines based on factory calendar - is The Book wrong?
> > 
> > Hello all,
> > 
> > We have a requirement to calculate the deadline for a 
> > workitem (eg Latest
> > Start) based on the Factory Calendar.
> > 
> > For example, if the workitem was created on a Thursday and 
> > the 'Latest Start' deadline is +3 days, then it should be 
> > triggered on the following Tuesday (not Sunday). In other 
> > words, it should only take working days into account.
> > 
> > Surprisingly, SAP standard does not cater for this scenario. 
> > I therefore implemented the solution suggested in the The 
> > Book, in Appendix A9. It shows you how to create a custom 
> > deadline object based on the factory calendar, and use the 
> > expression ZDEADLINE.DATE as the reference date in the step.
> > 
> > Surprisingly (again), this solution DOES NOT work. Deadlines 
> > are triggered without taking weekends into account.
> > 
> > When I had a closer look at it, I noticed that the Factory 
> > Calendar is only being used to determine the Workitem 
> > _Creation Date_; it is not being used to calculate the Latest 
> > Start Date. The book even seems to concede this:
> > 
> >       "Note that the reference date gives the date based on 
> > the factory calendar, but any offset will simply be added to 
> > the reference date as normal".
> > 
> > If this really is the case, then what is the point of 
> > implementing this solution?
> > 
> > Has anyone gotten it to work? I'm sure it must be me... sigh.
> > 
> > cheers
> > Paul
> > 
> > 
> > **************************************************************
> > **************************************************************
> > **************************
> > 
> > Only an individual or entity who is intended to be a 
> > recipient of this e-mail may access or use the information 
> > contained in this e-mail or any of its attachments.  Opinions 
> > contained in this e-mail or any of its attachments do not 
> > necessarily reflect the opinions of Queensland Treasury.
> > 
> > The contents of this e-mail and any attachments are 
> > confidential and may be legally privileged and the subject of 
> > copyright.  If you have received this e-mail in error, please 
> > notify Queensland Treasury immediately and erase all copies 
> > of the e-mail and the attachments.  Queensland Treasury uses 
> > virus scanning software.  However, it is not liable for 
> > viruses present in this e-mail or in any attachment.  
> > 
> > **************************************************************
> > **************************************************************
> > **************************
> > 
> > _______________________________________________
> > SAP-WUG mailing list
> > SAP-WUG at mit.edu
> > http://mailman.mit.edu/mailman/listinfo/sap-wug
> > 


-------------------------------------------------------------------
The information contained in this message may be CONFIDENTIAL and is
intended for the addressee only. Any unauthorised use, dissemination of
the
information or copying of this message is prohibited. If you are not the
addressee, please notify the sender immediately by return e-mail and
delete
this message.
Thank you.