Changed workflow on productive system

Mike Pokraka wug.replies at workflowconnections.com
Fri Sep 23 04:44:54 EDT 2005


Hi Robert,

All consutants' answers must start with 'Depends' :-) In this case:
Depends on the type of change, if it's a version independent change such
as the underlying code in a business object, it will execute
automatically.

If it's a version-dependent change, you're pretty much stuck with it. In
the past I've resorted to restarting and manually force the WF's back to
the original point using SWIA and manipulating containers.

Note 125400 has some good info on this.

Cheers
Mike

robert.van.den.berg at accenture.com wrote:
> Hello group,
>
> Bit of a common situation I think but: we discovered an error in a
> workflow on production. We corrected the error but we want this
> correction to be used in the already 'Active' workflows. Is it possible
> to do this?? The error is in a task which has not started yet...
>
> Thanx!
> Robert
>
>
> This message is for the designated recipient only and may contain
> privileged, proprietary, or otherwise private information.  If you have
> received it in error, please notify the sender immediately and delete the
> original.  Any other use of the email by you is prohibited.
> _______________________________________________
> SAP-WUG mailing list
> SAP-WUG at mit.edu
> http://mailman.mit.edu/mailman/listinfo/sap-wug
>


Mike Pokraka
Senior Consultant
Workflow Connections Ltd.
Mobile: +44 (0)7786 910 855


More information about the SAP-WUG mailing list