RE : Task Wait for event and deadline delay

Caillet, Eric Eric.Caillet at logicacmg.com
Tue Jun 21 08:09:18 EDT 2005


Dear Jocelyn,
 
thanks for your answer.
 
Well, in my business scenario i'm waiting a event, if the event arrive in the limit of work item creation + 2 days i take a action and if the event don't arrive at the limit i want to take a another action (for exemple, notification email).
 
What i don't understand this is why SAP put on the task deadline informations ? when i look the protocol's worklow and particulary the waiting a event task, deadline is arrived but the event is always in progress... it don't stop ?
 
Regards,
Eric C.

________________________________

De: sap-wug-bounces at mit.edu de la part de Dart, Jocelyn
Date: mar. 21/06/2005 05:03
À: SAP Workflow Users' Group
Objet : RE: Task Wait for event and deadline delay


Eric, 
 
It's not generally a good idea to put deadlines directly on terminating events such as "wait for event". 
I'm not clear on what you are trying to achieve in your business scenario.  Do you not want to handle the event at all if it occurs within 2 days of work item creation? Or do you want to take action at work item + 2 days regardless of whether the event has arrived or not?
 
 
Regards, 
Jocelyn Dart 
Senior Consultant 
SAP Australia Pty Ltd. 
Level 1/168 Walker St. 
North Sydney 
NSW, 2060 
Australia 
T   +61 412 390 267 
M   + 61 412 390 267 
E   jocelyn.dart at sap.com 
http://www.sap.com <http://www.sap.com/>  

The information contained in or attached to this electronic transmission is confidential and may be legally privileged. It is intended only for the person or entity to which it is addressed. If you are not the intended recipient, you are hereby notified that any distribution, copying, review, retransmission, dissemination or other use of this electronic transmission or the information contained in it is strictly prohibited. If you have received this electronic transmission in error, please immediately contact the sender to arrange for the return of the original documents. 

Electronic transmission cannot be guaranteed to be secure and accordingly, the sender does not accept liability for any such data corruption, interception, unauthorized amendment, viruses, delays or the consequences thereof.

Any views expressed in this electronic transmission are those of the individual sender, except where the message states otherwise and the sender is authorized to state them to be the views of SAP AG or any of its subsidiaries. SAP AG, its subsidiaries, and their directors, officers and employees make no representation nor accept any liability for the accuracy or completeness of the views or information contained herein. Please be aware that the furnishing of any pricing information/ business proposal herein is indicative only, is subject to change and shall not be construed as an offer or as constituting a binding agreement on the part of SAP AG or any of its subsidiaries to enter into any relationship, unless otherwise expressly stated. 

 

________________________________

From: sap-wug-bounces at mit.edu [mailto:sap-wug-bounces at mit.edu] On Behalf Of Caillet, Eric
Sent: Tuesday, 21 June 2005 12:55 AM
To: SAP Workflow Users' Group
Subject: Task Wait for event and deadline delay


Hi all,
 
i want that my workflow awaits an event so i've used task "Wait for event" and i want that this event is to subjected to a time constraint so, in my task i put information delay : "work item creation" + 2 days. Ok. Now, when the deadline is arrived, in the workflow's protocol i can watch that the deadline is arrived but workflow don't connect to other connection like obsolete or deadline.
 
Can i do that ? If not how can i circumvent this ?
 
Thanks so much.
Eric C.


This e-mail and any attachment is for authorised use by the intended recipient(s) only. It may contain proprietary material, confidential information and/or be subject to legal privilege. It should not be copied, disclosed to, retained or used by, any other party. If you are not an intended recipient then please promptly delete this e-mail and any attachment and all copies and inform the sender. Thank you.
-------------- next part --------------
A non-text attachment was scrubbed...
Name: not available
Type: application/ms-tnef
Size: 7920 bytes
Desc: not available
Url : http://mailman.mit.edu/pipermail/sap-wug/attachments/20050621/0261a885/attachment.bin


More information about the SAP-WUG mailing list