Delay in background workitem

Kjetil Kilhavn KJETILK at statoil.com
Mon Jun 20 07:57:30 EDT 2005


Does it take long because the work items are waiting to start execution
(20 minutes .... start ... a few seconds ... completed), or because
performance is poor (a few seconds ... starts .... 20 minutes ...
completed)?
 
In the latter case I wouldn't think there is too much you can do by
customizing. You can possibly check whether available processes is an
issue.
In the former case I suppose your deadline handler is not running
frequently enough.
-- 
Kjetil Kilhavn, Statoil KTJ IT BKS
 


________________________________

From: sap-wug-bounces at mit.edu [mailto:sap-wug-bounces at mit.edu] On Behalf
Of Abdal Salam S. Sheikali
Sent: 20. juni 2005 13:34
To: sap-wug at mit.edu
Subject: Delay in background workitem 



Hi everyone, 

After upgrade from 4.6C to ECC 5.0, the execution of background
workitem's takes long time to complete (around 20 minutes), can we
change any settings of the workflow runtime system, or workflow
customizing to reduce the delay. 

 

Thanks 

Abed Al Salam Sheikali 



-------------------------------------------------------------------
The information contained in this message may be CONFIDENTIAL and is
intended for the addressee only. Any unauthorised use, dissemination of the
information or copying of this message is prohibited. If you are not the
addressee, please notify the sender immediately by return e-mail and delete
this message.
Thank you.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://mailman.mit.edu/pipermail/sap-wug/attachments/20050620/a95177fc/attachment.htm


More information about the SAP-WUG mailing list