Parked Document Workflow - Error in 2nd Release

Marc Correia Marc.Correia at fonterra.com
Wed Sep 8 23:45:53 EDT 2004


Hi Loila
 
They should be assigned at the task level.
 
Regards
Marc.
 
-----Original Message-----
From: HCMI FLORENDO, Loila V. [mailto:florendolv at hondamakati.com.ph]
Sent: Thursday, 9 September 2004 2:30 p.m.
To: SAP-WUG at MITVMA.MIT.EDU
Subject: Re: Parked Document Workflow - Error in 2nd Release
 
 
Hi Marc,
 
Here's how we designed the process for the workflow...
 
=20                               Acctg           Acctg           Acctg
Finance
=20                               Staff           Supervisor      Manager=
 
Manager
Amount Release Level                    (1)             (2)
(3)
---------------------------------------------------------------------
Create, Park, Complete  X
100K to 499K                            X
500K to 999K                            X               X
1 Million & above                               X               X
X
 
All single-level, two-level and three-level amount release workflow
templates contain the task TS00007914 (Release amount). When I assigned
the agent on the workflow template, no work item is sent to the agent.
But when I assigned the agents (Acctg Supervisor, Acctg Manage and
Finance Manager) to the task, all 3 agents received a work item.
 
On single-level amount release, it works fine. But when it comes to
2-level and 3-level amount release, it doesn't work.
 
What should I do? Should the agents be assigned to the task or to the
template level?
 
Best regards,
Loila
=20                 =20
-----Original Message-----
From: SAP Workflow [mailto:Owner-SAP-WUG at MITVMA.MIT.EDU] On Behalf Of
Marc Correia
Sent: Wednesday, September 08, 2004 7:47 AM
To: SAP-WUG at MITVMA.MIT.EDU
Subject: Re: Parked Document Workflow - Error in 2nd Release
 
Hi Loila
 
You might want to speak to your functional consultant. With release you
have different release groups that can be configured. That means when
the first approver releases, he releases e.g. group 1. That does not
mean the invoice is released however its available for the second stage
release If this config is not set up then you will surely run into
trouble.
 
Regards
Marc.
 
-----Original Message-----
From: HCMI FLORENDO, Loila V. [mailto:florendolv at hondamakati.com.ph]
Sent: Tuesday, 7 September 2004 9:27 p.m.
To: SAP-WUG at MITVMA.MIT.EDU
Subject: Parked Document Workflow - Error in 2nd Release
 
 
Hello everyone!
 
I've configured Workflor for Releasing and Posting Parked Documents. For
the single-level amount release, it's working fine. But for the
two-level amount release, I get this error on the second release.=20
 
=20       "Work item could not be accepted (->function canceled)
=20        Message no. WO 529"
 
Am I missing something?
 
Thank you all in advance.
 
Best regards,
Loila
-----------------------------------------------------------------------
This email contains confidential information. If you have received this
email in error, please delete it immediately, and inform us of the
mistake
by return email. Any form of reproduction, or further dissemination of
this email is strictly prohibited.
Also, note that the opinions expressed in this email are those of the=20
author and are not necessarily those of the Fonterra Co-operative Group
Limited.
http://www.fonterra.com/
-----------------------------------------------------------------------
-----------------------------------------------------------------------
This email contains confidential information. If you have received this
email in error, please delete it immediately, and inform us of the mistak=
e
by return email. Any form of reproduction, or further dissemination of
this email is strictly prohibited.
Also, note that the opinions expressed in this email are those of the=20
author and are not necessarily those of the Fonterra Co-operative Group
Limited.
http://www.fonterra.com/
-----------------------------------------------------------------------
 


More information about the SAP-WUG mailing list