Hi Alon,
 
We had a similar problem and we added the wait step, however you are
correct we have changed our workflow because of technical limitations.
 
Alon what I do not understand about your design is why parallel forks w=
hen
it seems to me that an activity B in fork B is waiting for activity A i=
n
fork A to raise and event for activity B to do something.  I would not =
have
had parallel forks at all but created a check after activity A that wou=
ld
check the result of activity A and created the activity B in the
appropriate leg of the check.
 
 
 
Regards
Nat Govender
Toyota South Africa
SAP Support  - SAP Workflow
Ext.              : 32645
Direct Line : 031 - 910 2645
Fax              : 031 - 902 9633
E-Mail         : ngovender4 at toyota.co.za
 
 
 
 
                                                                       =
 
             Alon Raskin                                               =
 
             <araskin at eOutlook                                         =
 
             .com>                                                     =
 To
             Sent by: SAP              SAP-WUG at MITVMA.MIT.EDU          =
 
             Workflow                                                  =
 cc
             <Owner-SAP-WUG at MI                                         =
 
             TVMA.MIT.EDU>                                         Subj=
ect
                                       Parrallel Forks and Parallel    =
 
                                       Processing                      =
 
             2004/03/08 06:16                                          =
 
             PM                                                        =
 
                                                                       =
 
                                                                       =
 
             Please respond to                                         =
 
               "SAP Workflow                                           =
 
               Users' Group"                                           =
 
             <SAP-WUG at MITVMA.M                                         =
 
                  IT.EDU>                                              =
 
                                                                       =
 
                                                                       =
 
 
 
 
 
Hi All,
 
We have a situation where a workflow calls two sub-workflows in a paral=
lel
fork. One of the sub-workflows does some processing and raises an event=
 .
The second sub-workflow needs to trap that event and handle appropriate=
ly.
It seems that the sencond sub-workflow is missing the event being raise=
d
because the first sub-workflow raises it before the second sub-workflow=
 has
a chance to reach the 'wait for event' step.
 
I know the obvious solution is to put a wait step for a few seconds to =
make
sure that the listening sub-workflow is ready but I hate that approach
because it feels like the 'wait step' is required due to technical
limitations rather then a business requirements. I know I could also ra=
ise
an event when the listening sub-workflow is ready and only then process=
 the
first sub-workflow but again this seems like modelling an event for the=
 
sake of the technology rather then the business process.
 
Has anyone else experienced this issue? I would appreciate your thought=
s
and possible solutions.
 