Which calendar is used for Latest end?
Svanikier, Helena
helena.svanikier at sap.com
Thu Dec 23 06:48:59 EST 2004
Hello Ute
No factory calendar is used to determine the various deadline options (latest start, latest end, ...). No difference is made between working days and others.
If you do want to include a factory calender then you will have to provide a method that calculates the dates the way you want. You can use the function modules from the function group SCA4 (i.e. FM END_TIME_DETERMINE).
Then use the calculated expression in the latest end customizing.
Regards
Helena
-----Original Message-----
From: sap-wug-bounces at mit.edu [mailto:sap-wug-bounces at mit.edu] On Behalf Of "Schröder, Ute Marion"
Sent: Mittwoch, 22.Dezember 2004 11:05
To: 'sap-wug at mit.edu'
Subject: Which calendar is used for Latest end?
Hi everybody,
I just received a question I was unable to answer
and looking in the book didn´t help me either.
If I have a Latest End defined in my workflow-Step, 3 Days after Workitem
Creation, which calender is uded to determine when 3 days are over.
Will say, if the workitem is created on friday, is 3 days later a monday or
would it be a wednesday?
Is there a way to determine which calender is to be used?
Thanx for all our help,
ute