Hi Michael,
Not at the task level directly but what you can do is use classification to assign a class to a task and then your substitution can relate to tasks with that classification.
Needs to be built into the workflow design of course but a viable option - plus it works for both position and user level substitution.
Regards,
Jocelyn Dart
Consultant (SRM, EBP, Workflow)
and co-author of the book
"Practical Workflow for SAP"
SAP Australia
email: jocelyn.dart at sap.com
phone: +61 412 390 267
fax: +61 2 9935 4880
-----Original Message-----
From: Michael Marten [mailto:michael.marten at philips.com]
Sent: Tuesday,8 July 2003 1:53 AM
To: SAP-WUG at MITVMA.MIT.EDU
Subject: substitution per standard task possible?
Hello,
I got this day a good question from an "inbox user":
can I define a substitution also for a standard task e.g. "QM task: Complete task"?