Hi Hans,
END_TIME_DETERMINE is one.
Regards,
        Jocelyn Dart
Consultant (SRM, EBP, Workflow)
and co-author of the book
"Practical Workflow for SAP"
SAP Australia
email: jocelyn.dart at sap.com
phone: +61 412 390 267
fax:   +61 2 9935 4880
 
 
 
 
 
-----Original Message-----
From: Hans Brilleman [mailto:Hans.Brilleman at capetown.gov.za]
Sent: Tuesday, 28 January 2003 7:17 PM
To: SAP-WUG at MITVMA.MIT.EDU
Subject: Function module to calc date for task start delay
 
 
Hi all,
 
Does anyone know of an function module where the import parameters are
date and amount of days, and the export gives the new date accoring to
the factory calendar. Ineed this to work both in to the future and into
the past.
 
Many thanks,
 
Hans.
 