AW: Possibility of a workflow in 4.6c

Schmidinger, Heinz (Unaxis IT BZ) heinz.schmidinger at unaxis.com
Tue Aug 5 02:21:46 EDT 2003


Hi Kane,
 
I belive it should be possible.
 
Satus-change to WOM could be the starting Event for a Workflow;=20
than a waiting step waiting for missed material comes on stock e.g. ( =
this I
think must be a customer-event, I haven't seen a useful =
Standard-Event),
follwoed by a  task to inform the planner maybe based on MKPF or =
Workorder.
 
hope it helps.
 
regards=20
 
Heinz
 
-----Urspr=FCngliche Nachricht-----
Von: Kane, Rajiv [mailto:Rajiv.Kane at conocophillips.com]
Gesendet am: Dienstag, 5. August 2003 06:00
An: SAP-WUG at MITVMA.MIT.EDU
Betreff: FW: Possibility of a workflow in 4.6c
 
Hi!
Is it possible to create a workflow for the following scenario?:
 
When maintenance have a work order but require a spare which is not in
stock, the planners put the W/O on hold WOM (waiting on materials)
purchasing buys the part. When the warehouse goods receiving enters the
arrival of the part in SAP does SAP automatically link (or can it be
configured to) and inform the planners that the part has arrived via =
the W/O
linked number???
 
Thanks,
 
Rajiv Kane
 