Purchase Requisition Workflow - Editing after Rejection

Jose Burgman [AST] jose.burgman at ast.co.za
Wed Oct 30 09:44:32 EST 2002


Why don't you make it so that the user must explicitly complete the work =
item?
 
Jose
 
-----Original Message-----
From: Abby Dywan [mailto:abby.dywan at us.ibm.com]
Sent: Wednesday, October 30, 2002 4:30 PM
To: SAP-WUG at MITVMA.MIT.EDU
Subject: Purchase Requisition Workflow - Editing after Rejection
 
 
Hi all -
 
We have modified the standard purchase requisition workflow to send the
purchase requisition back to the creator after rejection.  When the =
creator
opens the purchase requisition and makes changes, the workflow should
re-start.
 
We have this situation working except for one problem.  When the creator
opens the purch req and simply closes out of it again - without saving,
without making any changes at all - the workflow re-starts anyway.  I =
think
this has to do with the method for the business object BUS2009.Edit =
being
synchronous, but I can't seem to think of a way around it.  How can I =
fix
it so that the workflow only re-starts when changes have been made?
 
Any suggestions would be appreciated - thanks!
 
Abby  :)
______________________________________________
 
"This information is intended only for the person or entity to which it is addressed and
may contain private, confidential, proprietary and/or privileged material and may be subject
to confidentiality agreements.
 
Any review, retransmission, dissemination, or any other use of or taking of any action in
reliance upon this information, by persons or entities other than the intended recipient,
is prohibited.
 
If you received this in error, please contact the sender and delete the material from all
storage media.
 
The company is neither liable for proper, complete transmission of the information contained
in this communication, any delay in its receipt or that the mail is virus-free"
 


More information about the SAP-WUG mailing list