Deadline Monitoring according to a schedule.

Ulrich Mende wug at mende-edv-beratung.de
Thu Apr 18 02:17:57 EDT 2002


Hi, Dan -
you can donload a presentation on this issue from
www.mende-edv-beratung.de/mende_asug_2001.ppt.
 
This contains the code of an object type ZDEADLINE which does the
required calculations. If you have your own object type, you could
simple copy the virtual properties from ZDEADLINE to it.
 
Best regards Uli
 
 
 
 
Dan Belenky <danb at pcf.com> schrieb am 17.04.2002, 21:14:34:
> I have setup deadline monitoring to give the user 3 hours before the deadline
> is reached.
> By this I mean 3 working hours.  If they receive an item late in the
> afternoon, it should not time-out until the middle of the next morning.
>
> Does anyone know of a way to do deadline monitoring according to some pre-set
> schedule (for example a workcenter schedule?).
>
> --
> Dan Belenky
> Sr. Application Analyst
> Pacific Coast Feather Company
> danb at pcf.com
> 206-336-2260
 