"Item not covered by a release strategy"

Sheth, Neeraja Neeraja.Sheth at fnc.fujitsu.com
Tue Jul 10 18:03:51 EDT 2001


Sherman
 
When we upgraded from 3.1I to 4.6C, no release strategy would get assigned to the new PRs. We found that we needed additional authorization : authorization for class type C_TCLA_BKA,  class type 32. We have added this authorization to the general SAP user profile so everyone has it. This resolved the issue for us.
 
Try executing SU53 immediately after creating a new PR line item.
 
 
Regards
 
Neeraja
 
 
 
> -----Original Message-----
>> From: Sherman S. Wright [SMTP:swright at lsil.com]
> Sent: Tuesday, July 10, 2001 4:31 PM
> To:   SAP-WUG at MITVMA.MIT.EDU
> Subject:      "Item not covered by a release strategy"
>
> Hi All -
>
> I wonder if anyone's had a problem similar to this:
>
> We use release strategies for our Purchase Requisition lines, and all
> has been working fine, across our complete landscape (DEV, QA, PRD),
> which are all 4.6B.  However, a few weeks ago, our DEV box was
> "upgraded" to Support Package 28 (it was at 25 prior to that), and now
> all of our PR lines get the message "Item ##### not covered by a release
> strategy".  Everything seems to be configured the same as the other
> clients, workflow verification is correct, all classifications are
> maintained, and "old" PRs will continue through workflow, but nothing
> new is covered by a release strategy.
>
> Any ideas?
>
> Regards,
> Sherman << File: Card for Sherman S. Wright >>
 