WF task not a potential task to be started

Dart, Jocelyn jocelyn.dart at sap.com
Mon Jul 2 20:27:00 EDT 2001


Hi Robin,
Event Simulation gives you a one-character code to the right of each
unsuccessful workflow explaining why it could not be started.
At the bottom of the report is a list of what these codes mean.
So have a look and see what the simulation is saying is the problem?
 
I assume you already have other workflows in this system/client and
you have checked the workflow runtime environment is operational
through transaction SWU3?
Regards,
        Jocelyn Dart
Consultant (BBP, Ecommerce, Internet Transaction Server, Workflow)
SAP Australia
Email jocelyn.dart at sap.com <mailto:jocelyn.dart at sap.com>
Tel: +61 412 390 267
Fax: +61 2 9935 4880
 
 
-----Original Message-----
From: Robin Sahasranam [mailto:Rsahasranam at worldbank.org]
Sent: Tuesday, 3 July 2001 5:52 AM
To: SAP-WUG at MITVMA.MIT.EDU
Subject: WF task not a potential task to be started
 
 
I am almost ready to implement a new Workflow task (WS).  However, the Event
Simulation for the task in the Production client shows as "Other receivers -
Tasks  which do not use this event". In the Development and Integrated Test
clients the Event Simulation for the task shows as "Potential tasks to be
started - Successfully started".
 
The task has been tested succesfully in Development and Integrated Test
client.
All the transports to the Production client have been successfully imported.
I
have run all the diagnostic steps, consistency checks on objects and tasks,
generated the business objects, verified  the event linkage is enabled and
the
task is activated and refreshed the org. environment.  No problems were
reported
in any diagnostic step. However the event simulation still shows the
workflow as
"Other receivers - Tasks  which do not use this event". I did not have to do
anything special in the Integrated Test client, for the workflow to be
started.
 
Will the workflow be successfully started when the triggering event is fired
when the application goes live? Do I have to do anything else to show that
the
workflow will be Successfully started in the Event Simulation.?
 
Thank you for your assistance.
 


More information about the SAP-WUG mailing list