Workflow Question
Carson, Wayne
Wayne.Carson at solvay.com
Wed Jan 31 09:33:50 EST 2001
I am continuing to work on my workflow project.
For the first step of my task, I have a method that reads a PID value. The
binding is now working. I am able to see the container element that stores
the PID value in both the task container and workflow container. Thank you
Todd.
The second step is a condition.
If the PID value has an "X", then I want to terminate the workflow. For the
subsequent events, if the condition is true, then I terminate the workflow.
Otherwise, I continue to the next step in the workflow.
On the graphical editor, both paths lead right back into the workflow. I
expected one leg to "split" and show as a termination. It appears that my
definition isn't correct for the two events or the condition is not properly
defined.
Is there a binding requirement for the two events?
When I execute the workflow, the notification of a change in the delivery
date on the PO happens regardless of the value in the PID.
Thank you,
Wayne R. Carson
Business Consultant - SAP
Technical Applications Team Leader
Solvay Information Technologies, Inc.
3333 Richmond Avenue, Houston, TX 77098
> * Office: 713/525-4143 Fax: 713/525-6795
> * wayne.carson at solvay.com Pager: 1-888-923-0943
>
>
More information about the SAP-WUG
mailing list